Electronics production and testing planning system (APS)
The planner combines the assembly of electronics with the supply of components, workplace preparation and test capability. This helps to avoid accumulating products that cannot be processed further.
The order sequence is based on the total amount of components and mainline load, but does not check the allowed alternative and subsequent programming or test capability. Collected products are waiting for the next stage, and an immediate change in the sequence may affect the terms of other orders.
How the solution works
- Orders are collected, product versions approved and the right amount of components.
- The line readiness, conversions and load of further programming and testing sites are assessed.
- Comparison of order grouping and start options by meetable terms.
- The planner approves the schedule and transfers the tasks for execution.
- Actual deviations and the need for a re-test are returned to the next scenario.
Key challenges
- Planning does not reflect actual production constraints
Solution capabilities
Component Readiness
The quantity suitable for the plan is assessed by the approved manufacturer code, alternative boundary and quality status.
Line conversion sequence
Orders are grouped according to actual preparation work and permissible process restrictions.
Programming and testing capability
The following steps, their equipment and the significant need for re-work are evaluated.
Alternatives to Disruption
A component deficiency or equipment failure indicates affected terms and enforceable sequence variations.
Business context
- Planning does not reflect actual production constraints
- The order sequence is based on the total amount of components and mainline load, but does not check the allowed alternative and subsequent programming or test capability. Collected products are waiting for the next stage, and an immediate change in the sequence may affect the terms of other orders.
- Confirmation of the order date being fulfilled for sale
- The available components alone are not enough to promise an order: assembly, programming and test capabilities are required. The overall plan allows checking these restrictions together. The customer gets a reasonable deadline, and the seller can offer another quantity or supply schedule if the original wish is not met.
Core features
- Component Readiness
- Line conversion sequence
- Programming and testing capability
- Alternatives to Disruption
Key integrations
- Enterprise resource planning system (ERP) / MRP
- Orders, needs, supplies and planned receipts of materials.
- Electronics manufacturing execution system (MES)
- Actual status of operations, delays and remaining work.
- Warehouse management system (WMS)
- Real availability of materials and reservations.
- Computerised maintenance management system (CMMS)
- Planned maintenance windows and facility inaccessibility.
Potential impact (%)
The ranges indicate an illustrative relative change in the metric under the stated assumptions. Results depend on the starting position and actual use of the solution. Percentages for different metrics must not be added together.
The length of the pending incomplete production
3–16%Decreasing
This illustrative scenario assumes that 15-40% of the capacity metric is affected by allocation and preparation. That share is assumed to fall by 20-40%. Company data is needed to verify both the addressable share and the resulting change.
Waiting for programming and testing for similar products is evaluated, while checking terms.
Rebuilding time for comparable order volume
3–16%Decreasing
This illustrative scenario assumes that 15-40% of the capacity metric is affected by allocation and preparation. That share is assumed to fall by 20-40%. Company data is needed to verify both the addressable share and the resulting change.
The actual conversion is measured, separating the planning solution from the technical failure.
Part of the electronic orders transferred to the customer in time
1–4%Increasing
Sample starting part - 80%. Assumption: 20-40% of the remaining cases involve unmatched assembly and test capacity; a solution would help solve 20-40% of these cases.
Orders transferred at agreed time are divided by all orders that had to be transferred during the period. Interferences in supply and internal planning of components are separated.
Conditional calculation scenarios. The assumptions have not been validated against client measurements.
When this solution is relevant
- The assembly plan appears feasible, but shared programming or electrical testing capacity cannot handle the planned volume.
- The missing material in the plan is replaced by an alternative whose technical use has not yet been confirmed.
Project scope and implementation
A planning tool that evaluates assembly and testing together is being developed or applied. If the system in use already forms an adequate schedule, it is sufficient to supplement the data on components, job preparation and test capability. A broader project involves a general replanning of these phases.
Further development options
- Comparison of planned and actual causes of conversions
- Revision of test capacity scenarios